A late construction payment needs more than another chasing email.
Payment delays are hardly unusual in construction.
An application is submitted, the payment date approaches and then nothing arrives.
The first response is usually commercial rather than legal. Someone sends an email, makes a telephone call or raises the issue at the next meeting.
That approach is understandable. Nobody wishes to create unnecessary friction on a live project, particularly when there is more work to complete and an important commercial relationship to maintain.
The difficulty is that commercial discussions do not stop contractual deadlines from running.
While your team is waiting for a response, your legal position continues to develop.
This is why a late payment needs more than another chasing email.
Before deciding what to do next, I recommend looking closely at three areas.
- Check The Payment Dates
Start with the contract rather than your usual payment routine.
- What is the due date?
- What is the final date for payment?
- When should the relevant notices have been served?
These dates matter because construction payment disputes are often determined by procedure as much as the underlying disagreement.
A team might have a perfectly reasonable commercial position but still create unnecessary difficulties by overlooking the contractual timetable.
Do not assume the date your accounts department normally expects payment is the date the contract provides.
Check.
- Review The Notices
The next question is what has been issued by each party.
If the paying party intends to pay less than the amount stated as due, the relevant notices and their timing require careful attention.
A Pay Less Notice should not simply be accepted because somebody has sent a document bearing that title.
Look at when it was served, what amount is being proposed and the basis upon which the calculation has been made.
The precise requirements and deadlines will depend on the contract, so check the relevant payment provisions rather than relying on a standard timetable.
Likewise, review your own documentation.
A dispute over £250,000 is not helped by discovering weeks later that an important notice was missed because everyone assumed somebody else had dealt with it.
This is one reason I place considerable emphasis on contractual discipline during live projects.
Small procedural mistakes have a habit of becoming expensive problems.
- Build The Chronology
If the payment remains unresolved, somebody unfamiliar with the day-to-day project might eventually need to understand what happened.
Make their job easier.
Bring together the contract, payment application, relevant notices, correspondence and supporting records.
Then put the key events in chronological order.
You should be able to explain clearly what was claimed, when it became due, what the other party did in response and precisely where the disagreement arose.
This exercise is useful even where adjudication never becomes necessary.
It exposes gaps in the evidence and helps the commercial team understand the strength of its position before deciding how firmly to proceed.
When Should You Seek Legal Advice?
Not every late payment requires adjudication.
Some issues are administrative, others are resolved through direct negotiation once the contractual position is made clear.
The mistake is assuming that seeking legal advice automatically means escalating the dispute.
Early advice should provide the opposite.
It should tell you where you stand, what deadlines matter and which options are commercially sensible.
Where payment has been withheld and informal attempts have failed, adjudication can provide a route to a decision that is binding unless and until the dispute is finally determined, with the adjudicator generally required to reach a decision within 28 days of the referral.
For a business carrying labour, materials and subcontractor costs, that speed matters.
The objective is not to create a dispute where one does not exist.
It is to recognise when a payment problem has moved beyond routine administration and protect your position before valuable options disappear.
If you are currently dealing with a delayed or reduced payment on a construction project, start with the contract, the notices and the chronology.
Those three checks will tell you considerably more than another chasing email.
contact us
Contact Samuel Okoronkwo
Get in touch today to speak directly with Samuel Okoronkwo for expert legal advice and assistance.
Blog
Related Articles
- Construction, Dispute Resolution
- Construction, Dispute Resolution